Abstract
Pavement construction work of a road surface which can put for the purpose of recycle of construction remainder soil that occurred on construction works etc. Into the sidewalk and factory site was accomplished. Use materials are construction remainder soil, sand, gravel, cement and solidification agent. A thing of mix proportion condition of the uniaxial compressive strength (7days) 10N/mm?Q was selected from the result of spare test and execution construction work was curried out. Satisfaction was almost obtained the result to go there was not occurrence of crack etc. As for execution road surface, too.